Amite River Basin Commision LADOTD Monthly Reports




Monthly Reports 2019

Jan-
Feb
LADOTD Report by Susan Douglas: DOTD Real Estate is working with USACE Real Estate to establish priorities for land acquisition. Utility relocation construction has started at US61 with American Midstream currently doing HDD for their 12 line. Relocation activities will continue in the US61 vicinity through the end of 2019. The contract for the update of the LA964 bridge will be negotiated shortly, and final review for the Construction Management at Risk Statement of Qualifications is underway for the LA19 and La67 bridges.
Mar-
Apr
DOTD Report by William Delmar: DOTD Real Estate is working on land acquisition priorities while waiting on right of way survey to be completed. Utility relocation construction has started at US61 with American Midstream wrapping up activities, and EnLink Midstream next to relocate their pipeline. Relocation activities will continue in the US61 vicinity through the end of 2019. The contract for the update of the LA964 bridge design has been awarded and notice to proceed will be issued the week of April 15th. The Construction Management at Risk (CMAR) consultant statement of qualifications has wrapped up and this contract for the LA19 and LA67 bridges should be soon.
Apr-
May
LADOTD Report by William Delmar: DOTD Real Estate is working with USACE Real Estate on land acquisition related activities. EnLink is currently relocating on the west side of US61. Entergy is planned to begin mobilization onto the site in mid-June. Relocation activities will continue in the US61 vicinity through the end of 2019. The LA964 design contract has received the notice to proceed, and plans are to select the CMAR (construction management at risk) consultant for LA19 and LA67 within the next 2 weeks. Currently DOTD is working on the CE&I (construction engineering and inspection) contract and plans to advertise by the end of the month or beginning of June.
Jul-
Aug
LA DOTD Report on DOTD activities for the CRDC Project by Susan Douglas: Real estate is working on advanced acquisitions right now. The Maps will be complete in September and they can begin acquisitions for the remainder at that time. On the west side of US61, the Entergy 138kV line has been raised, and all relocations required for construction of the shoofly have been completed. On the east side of US61, Marathon is working on their Horizontal Directional Drill. ExxonMobil will be mobilizing the Tuesday after Labor Day to begin their relocation. LA964 is currently in design with an anticipated bid date in early 2020. LA 19 and LA 67 were re-advertised for Construction Management at Risk (CMAR) and proposals are under evaluation.
Sep-
Oct
Real estate is working on priority acquisitions at this time for the entire project. On the west side of US61, the Entergy 69kV is scheduled to be relocated by mid-December, and CenturyLink is continuing their efforts. On the east side of US61, ExxonMobil has mobilized and is beginning their horizontal directional drill. LA 964 continues in design with an anticipated bid date in early 2020. A designer has been selected for LA19 and LA67 and will begin work in the next few weeks.
Oct-
Nov
Real estate is working on priority acquisitions at this time for the entire project. On the west side of US 61, the Entergy 69kV is scheduled to be relocated by mid-December, and CenturyLink is continuing their efforts. On the east side of US 61, ExxonMobil has completed their HDD and secured the site. They will return in February to do their tie ins. Demco is modifying their design to incorporate construction features requested by USACE, and Orx is anticipated to mobilize in the next month. LA 964 continues in design with an anticipated bid date in early 2020. A designer has been selected for LA19 and LA67 and will begin design shortly.
Dec-
Jan
Real estate is working on priority acquisitions at this time for the entire project. On the west side of US 61, CenturyLink is continuing their efforts. On the east side of US61, DEMCO is modifying their design to incorporate construction features requested by USACE, and Orx is completing the removal of their pipeline, and ExxonMobil is mobilizing to the site to begin preparation for tie in for the new pipeline. LA 964 continues in design with an anticipated bid date in early 2020. A designer has been selected for LA19 and LA67 and contractor selection is underway.


Monthly Reports 2020

Jan-
Feb
DOTD Report by Pat Landry: There are 64 total parcels they are acquiring for the CRDC Project. They have acquired 17 and have 22 in negotiations, and 22 others needing appraisals. Real estate is working on priority acquisitions at this time for the entire project. On the west side of US61, CenturyLink continues to work on finalizing their relocation. On the east side of US61, Demco, AT&T, and Cox are coordinating the design to incorporate construction features requested by USACE. Orx has completed the removal of their pipeline from the DOTD right of way, and ExxonMobil plans to tie in for the new pipeline by the middle of March. LA 964 continues in design with an anticipated bid date in early 2020. A designer has been selected for LA19 and LA67 and contractor selection is underway. They are working with and talking to Florida Gas. Florida Gas will have to do some relocation. The Corps has asked DOTD to do the bridge-work for the 964 bridge. They have a contract with an engineering firm and they are close to being complete with that. They should go to bid in the Spring on the 964 bridge. The Corps is doing the bridges on 61 and they should be bidding those out soon. The bridges at 19 and 67 are being done through a Construction Management at Risk process. This will deliver the product quicker by selecting an engineering firm to start with to get about 30% of the design done and then get a contractor to work with the engineering firm. This process should expedite those two bridges.
Apr-
May
DOTD Report by Pat Landry: Update on DOTD activities for the Comite Diversion Canal Project are as follows: Real estate is working on priority acquisitions at this time for the entire project. US 61 utility relocations are complete with the exception of Demco and AT&T which are being coordinated directly with USACE construction. All other utilities that have been identified as compensable are reviewing and negotiating their Construction Reimbursement Agreements. Currently there are some compensability determinations still in development at USACE. LA 964 design is complete with project award anticipated by the end of 2020. Contractor selection for the Construction Management at Risk (CMAR) process to be used for LA19 and LA67 continues, with contractor selection anticipated May 26, 2020.
Jun-
Jul
Real estate is working on priority acquisitions at this time for the entire project. US 61 utility relocations will be complete with the completion of the Demco/AT&T relocation currently underway. All other utilities that have been identified as compensable are reviewing and negotiating their Construction Reimbursement Agreements. Currently there are some compensability determinations still in development at USACE. LA 964 design is complete with project award anticipated by the end of 2020. For LA19 and LA67, the agreements for the consulting engineer and contractor are being signed, and the initial Construction Management at Risk (CMAR) workshop for this effort is anticipated prior to the end of the month.